Kusile Power Station Package 25

project Year: 

In August 2011, Esor were approached by Eskom to tender for the General Service piping contract at Kusile Power Station, which consisted of all the interface piping between the bulk supply systems and the terminations to the buildings on the power block.

The Contract was awarded to Esor in February 2012 with a mobilization date in April 2012. The Contract value is in the order of R340m with an estimated completion date of December 2014. We employ 175 labourers and operators on this contract.

The contract scope comprioses of the installation of MPVC piping which was later changed to HDPE piping.  The piping networks is for the supply of potable water, fire water and sanitary drainage.

The contract was successfully completed with a gratified client and excellent quality work.