J10 Pipeline

project Year: 
03/2014

This project was awarded to Esor Pipejacking division in March 2013.  The project required 21 jackings within a 6 month period.  The J10 pipeline, replacing the outdated J8 pipeline, will be 14km long starting at Simon Bekker Rd in Germiston and ending at Reservoir Rd in Boksburg.  Our scope also includes 1 stormwater canal crossing, 2 rail road crossings, 1 un-utilised railroad cutting, and 17 road crossings.  The project was completed in December 2014.